Patna
Adani Power’s $3 Billion (₹26,482 Cr) Bihar Bet: 2,400 MW Project to Boost State’s Energy Supply
1. Mega Investment in Bihar
-
Total Investment: USD 3 billion (~₹26,482 crore).
-
Project Capacity: 2,400 MW ultra super-critical thermal power plant.
-
Location: Pirpainti, Bhagalpur district, Bihar.
2. Project Structure & Timeline
-
Configuration: 800 MW × 3 units.
-
Model: DBFOO (Design, Build, Finance, Own, and Operate).
-
Commissioning Timeline: 60 months (5 years).
3. Power Supply Agreement (PSA)
-
Tenure: 25-year Power Supply Agreement (PSA).
-
Buyer: Bihar State Power Generation Company Ltd. (BSPGCL).
-
Beneficiaries: North Bihar Power Distribution Company Ltd. (NBPDCL) & South Bihar Power Distribution Company Ltd. (SBPDCL).
-
Winning Bid Rate: ₹6.075 per kWh (lowest bid).
4. Fuel Security – SHAKTI Policy
-
Coal linkage secured under Government of India’s SHAKTI Policy, ensuring:
-
Stable fuel supply.
-
Reduced input cost risks.
-
5. Employment & Economic Impact
-
During Construction: 10,000–12,000 jobs (direct + indirect).
-
Post Commissioning: ~3,000 permanent jobs.
-
Boost to local economy via infrastructure and auxiliary industries.
6. Adani Power’s National Position
-
Part of the Gautam Adani-led Adani Group.
-
India’s largest private thermal power producer.
-
Installed Capacity: 18,110 MW (prior to this Bihar project).
7. Financial Takeaways
-
₹26,482 crore investment = one of the largest private sector power commitments in Bihar.
-
Long-term revenue stream locked through 25-year PSA.
-
Competitive tariff of ₹6.075/kWh strengthens market position.